Opening of new Private Sidings/Private Freight Terminals:
(Greenfield projects) (When consultant is engaged)

Sl. No.

Service

Time limit

Single Window Agency
(to be contacted for progress/non-compliance)

1.1

In Principle approval

30 days

CTPM (ctpm@wcr.railnet.gov.in)

1.2 (a)

Detailed Project Report (DPR) approval

30 days

CTPM (ctpm@wcr.railnet.gov.in)

1.2(b)

Drawing Approval

30 days (without bridges)
60 days(with bridges)

CE(G)
(cegn@wcr.railnet.gov.in)

1.2(c)

Estimate Approval

30 days after date of submision

Sr.DEN(Co) of concerned division

1.3

Divisional certification after execution of the works

30 days

Sr.DOM & Sr.DEN(Co) of concerned Division

1.4

Signing of siding agreement

15 days

Sr.DCM of concerned division

1.5

Notificationafter certification

5 days ( after receipt of Completion Certificate and signing of siding agreement and land agreement)

CCM/FM (ccmfm@wcr.railnet.gov.in)

Activities to be performed by the party
1) Submission of application with feasibility report and conceptual / schematic plan.
2) Remittance of Rs.15000/- (non-refundable) towards feasibility study fee drawn in favour of Chief Cashier/FA&CAO/WCR.
3) Application for RTC to Railway Board either by Railway or by the party.
Activities involved by Railway

1) Examination of the proposal with regard to feasibility, adequacy and flexibility.
2)Time limit: 30 Days